How To Attach Drip Edge

What kind of nails do you use for drip edge?

The drip edge is nailed in place using 1-1/2 galvanized roofing nails. A felt-tip marker works great for marking cuts. And, again, prying open the end with a small flat bar allows the pieces to overlap cleanly.

Can you screw in drip edge?

Install the drip edge by fitting it on the roof eave, pushing it tightly against the edge of the plywood and nailing or screwing it down. Use 1-inch galvanized roofing nails or 3/4-inch exterior screws. Space the fasteners by about 12 inches.

Where do you nail drip edge?

Nail the drip edge to the roof deck with minimum 12-gage roofing nails spaced 8 to 10-inches on center and 1-½ to 3-inches from the edge of the sheathing. Adjacent drip edge pieces should be lapped minimum 2 inches. Asphalt shingles should overhang the exterior edge of the drip edge by ¼ to ¾-inch.

Can you put drip edge on after shingles?

The drip edge is often replaced when new shingles are installed, but it can be replaced at any time. Asphalt roof shingles can become brittle in cold weather, so wait until a warm (but not hot) day to remove and replace eave stripping.

Do you nail down drip edge?

Nail high up on the drip edge so that the shingles will cover the nails. Ideally, you’d nail about every 12 inches, and in no circumstances should you have 16 inches or more between nails. When you place the next drip edge piece, it should overlap the first by an inch.

Do you put drip edge on before tar paper?

Installing roof drip edge flashing properly The best way is to install the roof drip edge only along the eaves first, then place ice-and-water barrier (in the snowbelt) or felt paper (underlayment) over the drip edge. This lets any water that gets on the roof run down the underlayment and over the drip edge.

Is drip edge nailed to fascia?

The correct placement of a roof drip edge is on top of the roof’s exterior cover directly between the sheathing and the fascia board, which forms a drainage gap between the drip edge and the fascia board. As a result, the drainage improves water flow and protects the roof from potential water damage.

How far should shingles hang over drip edge?

Shingles should be installed over the drip edge a minimum of 3/8” (9 mm) at both the eave edge and the rake edge. If the drip edge extends… out from the rakes and eaves (typically called DL Style or D Type), the shingles may be installed flush with the drip edge.

How many nails do you use on drip edge?

Install the starter strip so that it overhangs the drip edge by 1/2-inch. Nail the starter strip about 3” up from the leading edge, using 4 nails evenly spaced for a full strip (approximately 10”-12-inches apart).

How far should drip edge be from fascia?

Drip edge height: 1 5/8″ Drip edge lip extension: 1/2″ Recommended drainage gap: 1/4″ (approx) spaced off of the fascia board.

Does drip edge go over or under underlayment?

According to most building codes and manufacturer recommendations, the drip edge should be installed beneath the underlayment along the eaves of the roof. But over the underlayment along the rake edges of the roof. Understanding the proper way to install the drip edge will only get you so far.

Does the gutter go behind the drip edge?

It is recommended that gutters are placed under or ‘behind’ the drip edge of your roof. If gutters are installed below the drip edge, water can drip behind the gutter and cause damage to the wood supporting the gutter system.

Is drip edge on roof necessary?

Without a drip edge, water may end up beneath the shingles and may cause damage to various parts of the home. Though your home may not have originally had a drip edge installed, drip edges are now required by most building codes across North America to protect homes from damage.

How do you attach drip edge to an existing roof?

Make sure the outer edge extends over the gutter. If it doesn’t, pull the drip edge out slightly from under the shingles. Secure the drip edge with roofing cement. Apply a continuous bead of cement along the top of the drip edge, then press down on the shingle.

Does drip edge go around entire roof?

Drip edge is installed around the whole perimeter of the roof. It is used to hold the underlayments down and create a watertight seal around the edge of the roof. Only the face of the metal is seen and is usually just white one to one and half inch stripe located right under the shingles and above the fascia.

What is the difference between drip edge and rake edge?

It involves the point of application in relation to the underlayment and/or eaves flashing. At the rake edge, the perimeter drip edge metal is applied over the underlayment with the appropriate fasteners secured every eight (8) to ten (10) inches on center.

Is a drip edge necessary on a shed?

Shed roof drip edge is essential in keeping your structure watertight. However, there are tons of ways to mess up a drip edge installation. For instance, nailing drip edge too close to your shed will still allow drips down the fascia board.

Can you nail into fascia?

3) Secure the panel to the bottom of the fascia board with painted aluminum trim nails. Nail every 24″, but do not nail too tight. Nails should penetrate a minimum of 3/4″ into nailing surface. Pre-drilling hole slightly larger than nail diameter is recom- mended.

Does fascia go on before shingles?

Fascia and soffit are installed after the roof installation is finished. It is ideal that soffit and fascia materials be installed before you place tiles or any other type of roofing material on the roof.