Calculation of quantity of material for 12 mm thick plaster of ratio 1: 6 (1 Cement:6 Sand) in the wall for 100 Sqm

  1. Quantity of Cement = 2/(1+6) × 1 (1 Ratio of cement)
  2. In Kg = 0.30 × 1440 (Density of cement = 1440 kg/m3)
  3. Quantity of Sand = 2/(1+6) × 6 (6 Ratio of sand)
  4. In Cubic Feet = 63.558 cft (1 Cum = 35.31 cft)

How do you find sand and cement in plastering?

Mortar Calculation for Plastering work

  1. Density of Cement = 1440 kg/m3.
  2. Sand Density = 1450-1500 kg/m3.
  3. Density of Aggregate = 1450-1550 kg/m3
  4. How many KG in 1 bag of cement = 50kg.
  5. Cement quantity in litres in 1 bag of cement = 34.7 litres.
  6. 1 Bag of cement in cubic metres = 0.0347 cubic meter.

How do I calculate how much plaster I need?

Subtotal material cost = cement cost + sand cost = 28 + 25 = INR 53. step 4 :- labour rate and charges:- labour rate and cost for internal wall plastering is INR 15 to 18 per sq ft or INR 161 to 193 per sq m, consider labour rate and cost in this calculation is INR 180 per sq meter. Total cost = 233 + 35 = INR 268.

How much does sand way?

Approximate Weights of Various Construction Material Per Cubic Yard

Material lbs./ cu. yd. tons/ cu. yd.
Sand, dry, loose 2619 1.30
Sand, wet 3186 1.59
Sandstone 4023 2.01
Slag, bank 1890 .94

How many bags of cement do I need for a 2 bedroom house?

For a medium size of a 2 bedroom flat, it will take 2,200 blocks and 125 bags of cement.

How much sand and cement do I need for plastering?

The ratios mentioned in plastering are volumetric ratios of Cement & Sand (Ex. Cement:Sand = 1:5, 1 part of cement and 5 parts of sand in a mortar). The overall thickness of plastering should be minimum 20mm including two coats. The Volume of each cement bag = 50Kgs/1440 = 0.0348 m3.

What is the correct mixture of cement and sand?

What Is the Correct Ratio of Sand to Cement for Masonry? For general purposes, mix 6 parts sand to 1 part cement.

What is the difference between plastering and skimming?

They are both used to decorate buildings and increase the durability of a wall, but skimming is done to upgrade an old building whereas plastering is done to a new one. Another difference between skim and plaster is that plaster surfaces are always rough whereas a skimmed surface is smooth.

How much does it cost to plaster a room?

The cost of plastering a room depends on the size of the room, as mentioned above. Typical costs for a small room with a complete replastering all the walls of a small room would range from about £400 to £700, while simple reskimming would come in at £300 to £500.

How many 50kg bags of cement are in a cubic meter?

Procedure To Calculate Cement Bags In 1 Cubic Meter: Weight of 1 bag cement = 50 kg. =0.0347 cum. = 6.25 bags.

What area can a bag of cement plaster?

1 bag of cement will cover 13.04m² Area Now assuming 50m² area is require to be plaster on site.

How many 20kg bags of cement are in a cubic meter?

one 20kg bag will cover an area of 1.1m2 to a depth of approximately 10mm. or 108 x 20kg bags equates to one cubic metre of mixed concrete.

Which sand is best for plastering?

Basically river sand are used for any plastering work. Generally, in any plastering work plasterers are used natural sand, crushed stone sand or crushed gravel sand.which sand is best for plastering ?

IS Sieve Size %age Passing
2.36 mm 95 – 100
1.18 mm 90 – 100
600 micron 80 – 100
300 micron 20 – 65

How do you calculate sand?

How much sand do I need?

  1. Determine the length and width of the cuboidal excavation.
  2. Calculate the area of the excavation by multiplying the length by the width.
  3. Establish the depth of the excavation.
  4. Multiply the area by the depth of the excavation to obtain its volume: 36 * 0.5 = 18 cu yd .

What is the formula to calculate quantity?

EOQ formula Multiply the demand by 2, then multiply the result by the order cost. Divide the result by the holding cost. Calculate the square root of the result to obtain EOQ.

How many 25kg bags are in a bulk bag?

So how many 25 kg bags are there in a 1000kg bag. Hmmmm, tricky. yep, 40 it is.

How much is a plasterer per day UK?

Plasterers don’t only charge per job or per day. They also charge by the hour as well. A typical hourly rate, depending on whereabouts you are in the country but can be from £8 to £19 per hour, with a median of about £12 per hour.

Is skimming cheaper than plastering?

Cost of re-skimming a room If your walls are already in good condition, you may only need to re-skim your room. This typically involves adding a 5-8 mm layer of finishing plaster over the top of existing plaster walls. So, it’s a lot cheaper than plastering a room from scratch.

How much area does a bag of plaster cover?

bags the coverage is 4-6 square metres per 25kg. bag.

What is the ratio of water to plaster?

Generally, you’ll want to use approximately a 1:1 ratio of plaster to water—in other words, half and half.

How many bags of cement do I need for 1 cubic meter?

Thus, the quantity of cement required for 1 cubic meter of concrete = 0.98/0.1345 = 7.29 bags of cement.

Which cement is good for plaster?

Ordinary Portland cement (OPC),Portland slag cement (PSC) and Portland pozzolana cement (PPC) are available in Indian market and are used for plastering work.

How much should plastering cost?

Replastering Walls Repairing or re-skimming over existing plaster to correct blemishes in plaster. For a small room, prices range between £380 and £500. For medium rooms, you can expect to pay from £420 and £550 respectively. Average duration is between 1 and 2 days depending on the size of the room.

How many bags of cement are needed to plaster a room?

To plaster 1 room, you’ll need 6 bags of cement since you’ll need about 3 bags to plaster the internal walls.

What area does a 25kg bag of plaster cover?

One 25kg bag of magnetic plaster will cover five square-metres if applied at 3mm thickness.

How much is 1m3 of sand?

A cubic meter of typical sand weighs 1,600 kilograms 1.6 tonnes.

How many bags of cement do I need to plaster a 2 bedroom flat?

How Many Bags Of Cement And Sand Will Plaster 2 Bedroom Flat? For a 2 bedroom flat, you’ll need 16 bags of cement along with 1 20 tonnes trip of sharp sand (you’ll have a remainder. You’ll need some red sand too.

What area does a bag of multi finish cover?

Well if you go by the spec a bag of Multi and Board finish will cover 10.25-75 m2 at a coverage of 2mm on Plaster board. As the manufacturer will tell you this is, of course, just a guide.