QA

Question: How To Estimate Concrete Yardage

Just follow these steps: Measure the area in feet. Multiply length by width, and then by thickness. Divide the resulting number by 27 to find cubic yards.

How much concrete do I need for a 10×10 slab?

The amount you will need for a 10 x 10 slab is 1.3 cubic yards, we always add an extra 10% to allow for any slab depth variations or spills that may occur.

How many yards of concrete do I need for a 24×24 slab?

For example, for a concrete slab that is 24′ X 24′ X 4”, simply enter 4 in the Thickness/Depth field, 24 in the Width field, and 24 in the Length field. Click “Calculate”. Your answer should be 7.11 yards. Note: The Concrete Volume Calculator can also be used to determine yardage for aggregate products.

What’s the formula for estimating concrete?

Use the formula. Calculating the volume for concrete requires using three dimensions: length times width (which is area) times the height (thickness) or L x W x H. If you are using feet as your standard unit of measurement, this formula will give you the volume of concrete in cubic feet.

How many square feet is a yard of concrete 4 inches thick?

One Cubic Yard of Concrete: 4-inches thick – covers 81 square feet.

How much area does a 40 lb bag of concrete cover?

Regarding this, how much does a 40 lb bag concrete cover, as 133 lb concrete = 1 CF, so a bag of 40 lb concrete = 40/133 = 0.30 CF, therefore, a 40 lb bag concrete approximately cover around 1.8 square feet area upto depth of 3 inch.

How thick do I need my concrete?

Standard concrete floor slab thickness in residential construction is 4 inches. Five to six inches is recommended if the concrete will receive occasional heavy loads, such as motor homes or garbage trucks. To prepare the base, cut the ground level to the proper depth to allow for the slab thickness.

How much does it cost to pour a 24×24 slab of concrete?

A typical 24×24 garage slab costs between $3,057 and $5,944 with prices ranging from $5.31 to $8.31 per square foot for a 4” reinforced slab of concrete, and $6.83 to $10.32 per square foot for a 6” slab of reinforced concrete.

How many 80 lbs bags of concrete make a cubic yard?

One 80lbs bag of Quikrete Concrete Mix will yield approximately . 60 cu ft. So it will take 45 bag to equal one cubic yard of concrete. If you have a project over a 1/2 a cubic yard you should consider our Mix On-site Concrete especially if you are hand mixing.

How many sq ft does a yard of concrete cover?

How much concrete is in a yard? Concrete volume is measured in cubic yards. When poured on a perfectly level surface, one cubic yard will cover 27 square feet at one foot thick.

How many bags of concrete do I need for a 10×10 slab 4 inches thick?

The thickness of your 10′ x 10′ slab will determine just how many bags you need. The average thickness of a 10′ x 10′ concrete slab for a shed is 4 inches thick. At 4″ thick, your 10 x 10 slab will take 56 bags of concrete that weigh 80 lbs.

How many yards of concrete does a concrete truck hold?

Each cubic yard costs about $65. However, a fully loaded cement truck will hold 10 cubic yards—and partial “short” loads cost $15 to $20 extra for every cubic yard less than a full load.

What is ideal temperature to pour concrete?

Experts agree—the best temperature to pour concrete is between 40° – 60°F. When temperatures dip below 40°F, the chemical reactions that strengthen concrete slow down and can lead to weaker concrete.

How many cubic feet is an 80 lb bag of concrete?

45 cubic feet and an 80-pound bag yields . 60 cubic feet. One 50-pound bag of Quikrete Fast Setting Concrete Mix yields about . 375 cubic feet.

How much does a 90 pound bag of concrete cover?

A: QUIKRETE® Concrete Mix will yield approximately 0.675 cubic feet per 90-pound bag when mixed. For a pour of 15 feet by 10 feet at 5 inches thick, you will need 62.5 cubic feet of concrete, or 93 90-pound bags.

How many square feet does a 60 lb bag of concrete cover?

@ 2″ thick a 60 lb bag of concrete will fill 2.7 sq. ft. @ 4″ thick a 60 lb bag of concrete will fill 1.35 sq. ft.

Do you need rebar for 4 inch slab?

The thickness of rebar should be no more than 1/8 that of the slab, so a 4” slab shouldn’t have steel greater than #4 or 1/2″ bar. It’s best to check with a Structural Engineer if your slab will bridge or cantilever. What is this? For 4” concrete slabs used for driveways and patios, #3 rebar is common.

How many pounds can 4 inches of concrete hold?

Typically we like to limit the weight to about 40 lb/sqft on an unknown 4″ slab. In most cases you can go to 80 lb/sqft in isolated spots, but unless you know roughly what the soil bearing and reinforcing is for that slab you might be looking at cracking.

How strong is 4 inches of concrete?

A concrete patio slab should be at least 4 inches thick and have a compressive strength of 3,000 PSI.

How much concrete do I need for a 30×30 slab?

18 yards of 3000 psi concrete mix @ 135.00 per yard. Wire mesh reinforcement. A double row of #4 rebar around the edges. Labor to form the slab.

How much would it cost to pour a 30×40 concrete slab?

How much does a 30×40 concrete slab cost? The average cost is $4 to $8 per square foot. The median price is about $6 per square foot. Based on these averages, you may pay $4,800 to $9,600 with a median estimate of $7,200.

How much concrete do I need for a 40×60 shop?

How much does a 40×60 concrete slab cost? It would be about $8,500 to $12,000 for a 40×60 foot concrete slab, 6 inches thick. That’s based on national averages of around $5 per square foot for a fully engineered, finished concrete slab, including labor and materials.